Operational assets

Elga-Ulak railway line

Key facts
Cargo base
coal from the Elga deposit, as well as other auxiliary cargo (explosive materials, fuels and lubricants, spare parts and equipment)
Length
360 km, connects ECC with the Baikal-Amur Mainline
working hours
24-hour operation, 365 days a year
Development history
2011
completion of construction work by the previous owner
2020
expansion of throughput capacity up to 12 million tonnes / year
2021
expansion of throughput capacity up to 24 million tonnes / year
2023
expansion of throughput capacity up to 30 million tonnes / year
Expansion plan
Stage 01
Expansion of throughput capacity up to 18 million tonnes
Construction work at the Elga station (phase I)
Construction of a handling and warehouse complex at the Elga station (phase I)
Different railway works on the section 317 km - Elga station
Installation of utilities (power supply, communications, waveguide, signaling system)
Construction of auxiliary buildings
Stage 02
Expansion of throughput capacity up to 20 million tonnes
Construction work at the Elga station (phase II)
Construction of a handling and warehouse complex at the Elga station (phase II)
Laying of additional railway passing sidings
Development of the railway station
Auxiliary buildings
Stage 03
Expansion of throughput capacity up to 24 million tonnes / year
Construction work at the Elga station (phase III)
Construction of a handling and warehouse complex at the Elga station (phase III)
Laying additional railway passing sidings
Development of railway station A
Auxiliary buildings
Implementation of an automatic block signaling system
Stage 04
Expansion of throughput capacity up to 28 million tonnes / year
Construction work at the Elga station (phase IV)
Construction of a handling and warehouse complex at the Elga station (phase IV)
Laying additional railway passing sidings
Development of railway switches
Development of railway stations
Auxiliary buildings
Stage 05
Expansion of throughput capacity up to 30 million tonnes / year
Construction work at the Elga station (phase V)
Construction of a handling and warehouse complex at the Elga station (phase V)
Development of railway switches
Development of railway stations
Auxiliary buildings